VBC New Campus Update

Welcome to the VBC New Worship Center Update page.

Here you will find the latest information on the progress we are making in the construction of our new Worship Center and its development located at 2401 Taylor Ranch Trail. Check back often to keep up with our progress.

May 22, 2019 Zoning meeting update:

Pastor Brett reported to elders as follows…..

“The zoning meeting went well last evening. There were 11 people from the surrounding communities and one deacon from colonial Baptist along with a gentleman from the county who led the meeting.

From VBC were Richard Claybrooke, our civil engineer, Mike Monville, our GC, the Mattson’s, the Olson’s and me.

Some of the questions centered around parking lighting (how tall), traffic (what were our service times), programs and noise (somebody saw the article about Coastlife church and the noise complaints).

Everything went well and we answered questions and were done by 6:45.”

Here are the Professional Contractors we are working with:

Architect: Bill Niblock –  Florida Architecture, LLC

Construction Manager: Mike Monville – Heritage Builders Engineering and Construction

Civil Engineer: Richard Claybrooke – Claybrooke Engineering Associationes, Inc.

Move the interactive map below to orient yourself to the location.

Questions? See the FAQ below.

Frequently Asked Questions (FAQ)

Still have questions or concerns? Share them with the Building Committee by this link. Please put Building Committee Question in subject line.

Master Plan and size of New Campus

VBC New Campus Master Plan DRAFT

2401 Taylor Ranch Trail
Venice, Sarasota County, Florida 34293

Aerial view of Promise Park Property

The New Life Church building in the upper right corner is 15,000 sq feet, the larger structure is 10,000 the smaller addition 5,000, for comparison to our proposed 9,000 square feet structure.

Current Construction Plans